See what could hit the job’s margin.

Anvil found three issues. The evidence and next steps are ready for your review.

Hawthorne Medical OfficeNov 4, 2026
Anvil

6 records connected · Issue flagged

The work changed. The price is still unapproved.

A floor-wide revision affects mechanical, electrical, and fire protection work. Trade pricing and owner direction are still open before ceilings close.

Scope changed

24 rooms affected. Rough-in is already underway.

Still open

No signed price approval before November 9 ceiling closure.

Signed scope · Exhibit B, §4

Third-floor installation is based on the issued layout dated July 10. Relocation after installation and work arising from subsequent layout revisions are excluded from the base scope and must be submitted for review.

Morgan Lee · 2026-07-13
Email · Third-floor layout revision

The revised room layout shifts the third-floor overhead rough-in across 24 rooms. Please relocate these before the ceiling crew returns on November 9. Send the additional cost for review. This instruction does not approve a price.

Dana Shaw · 2026-11-03
Change register · CH-014

CH-014: Third-floor relocation. Price pending, approval pending. No signed change order found in the change register. CH-009, the earlier approved lobby revision, is already included in contract revenue.

Morgan Lee · 2026-11-04
Budget quote · Third-floor relocation

Budget quotes for the floor-wide revision: Alder Mechanical $60,000; electrical and fire protection adjustments $24,000. Ceiling release needs a coordinated sequence. Quote awaits review. It is not a committed cost or an owner-approved change.

Jordan Ellis · 2026-11-04
Two-week lookahead · Third-floor

Ceiling closure planned November 9. Relocation requires confirmation by November 5 to preserve the planned sequence. If missed, the superintendent estimates $12,000 for remobilization and a separate ceiling return visit. This allowance is a risk estimate, not a confirmed delay or charge.

Jamie Reed · 2026-11-04
Cost ledger · Baseline forecast

Approved cost budget: $7,410,000. Paid and approved cost records: $4,402,000. Total commitments: $7,100,000, including those recorded costs. Remaining committed cost: $2,698,000. Uncommitted cost to complete: $310,000. Baseline forecast: $7,410,000. Pending change exposure is evaluated separately in the scenario forecast.

Morgan Lee · 2026-11-04

Start with the evidence, then review the next step.