See what could hit the job’s margin.

Anvil found three issues. The evidence and next steps are ready for your review.

Birch Street ApartmentsNov 4, 2026
Anvil

3 records connected · Issue flagged

The forecast changed. The crane is booked.

Friday’s steel erection now overlaps rain and gusts. The crane, erection crew, and deliveries are committed; decking follows Monday.

Already committed

Friday’s crew, crane, and deliveries.

Decision needed

Superintendent’s review before booking deadlines.

Forecast snapshot · Nov 4

Scenario forecast: rain and stronger gusts now overlap the November 6 crane operation. This snapshot is not a live forecast or an operating limit. The superintendent must check current conditions, the lift plan, and equipment limits before deciding whether work can proceed.

Jamie Reed · 2026-11-04
Lookahead · Crane, crew & deliveries

November 6: steel erection crew, crane booking, and three steel deliveries committed for the east wing. Decking follows November 9. Confirm crane cancellation terms and delivery options by November 5 at noon. No standby or delay cost has been priced.

Jamie Reed · 2026-11-04
Field plan · Alternative work readiness

Candidate alternative: west-wing interior framing. Materials are on site and the layout is released, but corridor access is not confirmed. Another option is a later steel erection window, subject to crane, erection crew, and delivery availability. Neither option is released.

Jamie Reed · 2026-11-04