Anvil SystemsExplore a real project

Catch the cost before you carry it.

Anvil found three issues. The evidence and next steps are ready for your review.

Maple Public LibraryNov 4, 2026
Anvil

3 records connected · Issue flagged

The quote doesn’t match the approved package.

The supplier quoted a different rooftop-unit model and omitted an option. The purchase is not released.

Approved package

AC-120 × 2, with economizer option E.

Supplier quote

AC-120S × 2. Economizer not listed.

Approved submittal · RTU-03 Rev B

Approved rooftop-unit package: model AC-120, quantity 2, with economizer option E. Approval applies to this submitted package. Any alternative requires documented design review.

Alex Chen · 2026-10-20
Supplier quote · Q-418 Rev 2

Proposed purchase: model AC-120S, quantity 2, total $94,000; economizer option not listed. Supplier lists a six-week lead time from release. Quote expires November 6. No purchase order has been released for this package.

Taylor Brooks · 2026-11-04
Approval log · Equipment release

RTU-03 Rev B is approved. No approval for model AC-120S or the omitted economizer option is recorded. The planned December 14 equipment set is four days before December 18, the end of the quoted six-week lead time from November 6; delivery needs confirmation. Model differences alone do not establish technical noncompliance.

Jordan Ellis · 2026-11-04

Start with the evidence, then review the next step.