3 records connected · Issue flagged
The quote doesn’t match the approved package.
The supplier quoted a different rooftop-unit model and omitted an option. The purchase is not released.
AC-120 × 2, with economizer option E.
AC-120S × 2. Economizer not listed.
Approved submittal · RTU-03 Rev B
Approved rooftop-unit package: model AC-120, quantity 2, with economizer option E. Approval applies to this submitted package. Any alternative requires documented design review.
Alex Chen · 2026-10-20Supplier quote · Q-418 Rev 2
Proposed purchase: model AC-120S, quantity 2, total $94,000; economizer option not listed. Supplier lists a six-week lead time from release. Quote expires November 6. No purchase order has been released for this package.
Taylor Brooks · 2026-11-04Approval log · Equipment release
RTU-03 Rev B is approved. No approval for model AC-120S or the omitted economizer option is recorded. The planned December 14 equipment set is four days before December 18, the end of the quoted six-week lead time from November 6; delivery needs confirmation. Model differences alone do not establish technical noncompliance.
Jordan Ellis · 2026-11-04Start with the evidence, then review the next step.